MPH-02, MPB-02, MPD-02 Operating Modes 7-123
DOK-INDRV*-MP*-02VRS**-FK01-EN-P
The figure below illustrates the basic commissioning steps:
start
commissioning
scaling
(S-0-0076)
general parameterization
- linear/rotary scaling
- with linear scaling, parameterize feed constant
- enter load gear
- synchronization velocity and synchronization acceleration
absolute
absolute synchronization
- select synchronization mode
- relative or absolute synchronization
absolute parameterization
- determine S-0-0278, Max. travel
range (max. +/-2048 revs.)
modulo parameterization
- determine modulo range
- determine S-0-0278, Max. travel
range (min. S-0-0103)
modulo
modulo master axis
- parameterize P-0-0750, Master axis
revs. per master axis cycle
- with linear scaling, parameterize
feed travel of slave axis
- determine electronic gear
modulo synchronization
- select synchronization mode
- relative or absolute synchronization
- select synchronization range
- generation of actual value cycle
- parameterize actual value cycle
establish position
data reference
parameterization of cam shaft
- select cam shaft (active cam shaft, switch angle)
- parameterize cam shaft distance (value, change angle, activation)
- parameterize angle offset (change angle and change velocity)
- dynamic angle offset
- parameterize technology functions
(cross cutter, clocked pull roll)
- parameterize P-0-0750, Master axis
revs. per master axis cycle
- with linear scaling, parameterize
feed travel of slave axis
- determine electronic gear
absolute master axis
- only finite cam shaft
(initial value = final value)
- no gear reduction (P-0-0757)
Fig. 7-94: Overview of commissioning steps for cam shaft mode